CEO Johnson Tan interviewed by Bloomberg
On 4 March, Raimon Land PLC's CEO Johnson Tan spoke from Bangkok with John Dawson on Bloomberg Television's "On the Move" about his company's recently revealed financial report and its business outlook for this year. Raimon Land recorded a 50%t increase in profits during 2013 to reach THB746 million – an 11-year high for the Thailand property developer. |
|
Watch the video, please click here .
|
|
|
|
185 Rajadamri highlights Hong Kong roadshow
On 8-9 March, Raimon Land held a roadshow sales event at Conrad Hotel, Pacific Place, Hong Kong. Investors from Hong Kong and Southeast Asia showed strong interest in the developer's185 Rajadamri property, on the famed Rajadamri Road in the center of the capital |
|
|
|
|
|
Bank of China Bangkok visits 185 Rajadamri
On 11 March 2014, 185 Rajadamri welcomed Che Jun, the GM of Bank of China in Bangkok, and his management team. Mr. Che and Raimon Land CEO Johnson Tan discuseed potential strategic cooperations between their two companies. |
|
|
|
|
|
High-Tea Party to discover The River community
Recently, Raimon Land held an exclusive High-Tea Party at The River, partnering with MBK Guarantee, Thanachart Bank, and Bank of China. All 33 attendants got the chance to speak with financial consultants from the banks, the |
|
Raimon Land sales team and other investors. By the end of the day, a total of around THB100 million worth of units were sold which reflected investor confidence in Thailand and the attraction of Raimon Land properties.
|
|
|
|
The Lofts Ekkamai partner's with Playboy on its 60th anniversary
On 20 March, The Lofts Ekkamai partned with Playboy on its 60th anniversary party at KuDeTa, W Hotel Bangkok. Many Raimon Land buyers, potential buyers and partners attended the star-studded gala. |
|
|
|
|
|
Unixx South Pattaya opens new show suite next month
On 2 April, Unixx South Pattaya will unveil its new themed suite and furniture package, redefining the property as a true weekend hideaway or second home. Ownership at Unixx means you will enjoy all the benefits of one of the world's premier international vacation destinations. |
|
Pattaya has something for everyone and every mood. Fine dining, shopping venues, sporting life, party scenes, seaside living, and other top-notch amenities are all at your doorstep. And for those living and working in Bangkok, you can take off for Pattaya on a whim, at any time, as it is less than 2 hours away from the capital.
|
|
|
|
Construction update – 185 Rajadamri
Final cleaning of all external facades and completion of remaining decorations.
Architectural works are 98.5% complete and mechanical, electrical and sanitary trades are 99% complete.
Passenger lifts are complete with final balancing, testing and commissioning.
External works, hardscape and softscape are 99% complete, with a focus on completing the Sarasin Road entrance. |
|
The 7th floor Pool Deck is 99% complete. The gymnasium, sauna and Jacuzzi have been equipped and tested and furniture is being installed.
Residential units and common areas are 99% complete. Some internal architectural finishing works on the main lobby are still ongoing.
|
|
|
|
Construction update – Zire Wongamat
The Zire Wongamat comprises two residential towers – 37 and 54 storeys, respectively – with a, Beach Club, landscaped gardens and separate carpark building.
Tower A construction is complete.
Tower B construction is complete.
Carpark building is complete.
|
|
Architectural and MEP are advanced in Tower A and Tower B, with current work focusing on completion of residential units, common area details and Occupation Permit applications which are due at the end of Q1.
External roadway works have commenced and are planned to finish in time for the Occupation Permit.
|
|
|
|
Construction update – Unixx South Pattaya
Main building construction has now reached the 6th floor slab.
The slip-form sliding formwork for the lift core is now at the 8th floor.
Car park construction has reached the 3rd floor.
|
|
First residential units, pre-cast external walls and internal party walls are now being installed.
All tower cranes and concrete placing booms have been erected and are operational.
|
|
|
|
Construction update – The Lofts Ekkamai
Show units are complete and the sales office is open.
Environmental Impact Assessment has been awarded to the project.
Building Permit has been awarded to the project. |
|
Piling works will be complete by the end March 2014.
Tenders for the main building work are currently under negotiation. |
|
|
|