TH | ENG

Share with your friends                      

 

Season’s Greetings

Raimon Land would like to wish its esteemed homeowners and residents a very Merry Christmas and a Happy New Year. May 2015 bring you health, prosperity and joy.

 

Bloomberg Forum

Raimon Land was proud to sponsor the first ever Bloomberg ASEAN Business Summit in Thailand, at the Grand Postal Office on 2-3 December 2015.

The summit featured influential business leaders, dynamic entrepreneurs, and influential government officials discussing and debating AEC implementation, ASEAN economic development, and the global economy.

 

CEO Dinner

Raimon Land recently held a CEO dinner for clients, partners and friends on the evening 16 December 2014 at 661 Silom, an innovative ‘gastro bar and Dom Perignon lounge’. During the event, Raimon Land CEO Johnson Tan briefly discussed the firm’s new landed housing project in the Sathorn central business district.

 

LPS Shanghai 2014

With Chinese nationals making up an ever growing segment of Raimon Land’s residential communities, the company recently participated in Luxury Property Showcase Shanghai – the leading luxury real estate exhibition in China’s commercial capital – on 12-14 December 2014.

 

 

 

Fireworks Event

On 28-29 November 2014, Raimon Land sent a roadshow caravan to the Pattaya International Fireworks Competition 2014, one of the seaside resort community’s most colorful and exhilarating festivals.

 

 

 

Jet Ski Event

On 4-7 December 2014, Ramon Land featured a sales booth and roadshow caravan at the Kings Cup – Jet Ski World Cup, Thailand 2014, one of the world’s premier jet ski events in a city known for its fabulous array of water sports.

 

 

 

Q4 Promotions

Raimon Land is offering many interesting promotions* for all of its existing properties in Bangkok and Pattaya.

185 Rajadamri

  • No CAM Fee and Sinking Fund for 12 months
  • Family & Friends program (When you refer a buyer, each of you will receive THB 100,000)

The River

  • No CAM Fee and Sinking Fund for 12 months
  • Furniture package
  • Family & Friends program (When you refer a buyer, each of you will receive THB 100,000)

The Lofts Ekkamai

  • No credit card charge on your 10% contract fee
  • Special terms of payment for remaining units
  • Furniture package
  • Family & Friends program (Get THB 50,000 when you refer a buyer)

Zire Wongamat

  • No CAM Fee and Sinking Fund for 12 months
  • Furniture Package
  • Family & Friends program (When you refer a buyer, each of you will receive THB 100,000)

Unixx South Pattaya

  • Save up to 7% on your residence with our limited payment plan
  • Furniture package
  • Family & Friends program (Get THB 50,000 when you refer a buyer)
 

*All promotions are valid from 1 October to 31 December 2014. Certain conditions apply.

To learn more, contact our expert and experienced team by calling 0 2651 9600 or email direct.marketing@raimonland.com.

 

Construction update – The Lofts Ekkamai

  • Inner and outer Sheet Piling is 100% completed.
  • King Post installation is 100% completed.
  • Platform installation is 100 % completed.
  • Excavation layers 1, 2, 3 and 4 are 100% completed.
  • Bracing layers 2 and 3 are 100% completed.
  • Underground foundation works are 20% complete.

 

Construction update – Unixx South Pattaya

Structural works

  • Structural work of the car park has been completed. Pool structure on the podium rooftop is also completed, while the rooftop area is being prepared for the commencement of hardscape work.
  • The slip-form sliding formwork for the Lift Core is now at Level 41 and the main fire stairs have reached Level 33.
  • At the East Wing (the wing with higher building envelope), the floor slab has been completed at Level 38 while core wall has reached Level 40.
  • At the North Wing (the wing with lower building envelope), the floor slab has been completed at Level 36 while core wall has reached Level 38.

Architectural works

  • Pre-Cast external installation is fully completed at Level 21 and work has progressed up to Level 30.
  • Internal walls have been completed at Level 24 and work has progressed up to Level 31.
  • Ceiling work has been completed at Level 10 and has reached up to Level 23.
  • Door frames are being installed up to Level 23, while door panel installation is now at Level 14.
  • Tiles installation has reached Level 21.
  • Installation of the balcony balustrade has reached Level 15.
  • External painting work has progressed to 30%.
  • Internal painting work has reached Level 18.
  • Shower screen installation has reached Level 8.
  • Aluminum and glass window and door installation has progressed up to Level 16.
 

Mechanical & Electrical First Fix works

  • M&E First Fix works are at Level 40, whereas the 2nd Fix works are now at Level 34.
  • Lift installation has reached Level 22, with guiderails and brackets being installed.
  • CDU installation work has progressed up to Level 6.

Civil and External works have already been commenced, with 40% completion of the subterranean water tank work.

 