THE ESTELLE PHROM PHONG
Construction Progress as of December 2021:
77.24% Overall.
Structural Work: 99.85% Overall Completion.
Architectural Work: 83.98% Overall Completion.
MEP Work: 79.24% Overall Completion.
Façade Work : 64.30% Overall Completion.
Interior Work: 65.85% Overall Completion.
External Work: 44.54% Overall Completion.
Lift Work: 77.07% Overall Completion.