The
Lofts
Asoke
Construction
Update
as
of
End
of
August
2018:
Overall
92.14%.
Completed
Works:
Piling,
Soil
Protection,
Footing,
Passenger
Lift
Pit,
Mechanical
Car
Park
Lift
Pit,
Underground
Water
Tank
work,
Septic
tank,
Separation
tank
and
Grease
trap
Structural
Work:
Completed.
Architectural
&
Interior
Work:
81.97%
Overall
Completion.
Up
to
Level
45
MEP
Work:
90.48%
Overall
Completion.
Up
to
Level
45
External
Work:
Road
work
53%,
fence
work
40%
and
site
drainage
work
39%