The
Lofts
Asoke
Construction
Update
as
of
End
of
November
2018:
Overall
97.76%.
Completed
Works:
Piling,
Soil
Protection,
Footing,
Passenger
Lift
Pit,
Mechanical
Car
Park
Lift
Pit,
Underground
Water
Tank
Work,
Septic
Tank,
Separationtank
and
Grease
Trap.
Structural
Work:
Complete.
Architectural
&
Interior
Work:
96%
overall
completion.
Up
to
level
45.
MEP
Work:
99%
overall
completion.
Up
to
level
45.
External
Work:
Road
work
and
site
drainage
work
100%
complete;
fence
work
80%.