Northpoint Update

April 2010 construction works at the Northpoint project continued with the pace of construction activity being markedly increased as we approach the final weeks. Phased home owner inspections are ongoing and ownership transfers are being processed to take advantage of the extended transfer tax relief scheme.
Internally, apartment fit-out works are continuing towards completion commensurate with corridors, fire escape stairs and common areas. Building signage is being installed throughout the project. At both towers the external decorative paint finishes are now complete and external final cleaning of all facades, aluminium and glass and external louvers are being completed. The main entrance lobby fit-out works are now complete at both towers and are being furnished. The lift car fit-out works are now in process and two lifts per building have already been completed. Works to the sky gardens at level 29 tower A and level 24 tower B are now also practically complete. All management offices and back of house facilities are occupied and functional. MATV antennae are now installed and connected.
Externally, all the beachfront zone and area fronting tower B hardscape, softscape, swimming pools, slides and water feature works are complete. Tree planting and landscaping works to all remaining areas of the 12-rai site are likewise complete. Canopies to the car drop-off zones are installed and complete. The main entrance guard house and site boundary wall construction works are complete. Final finishes to the roads are currently being installed and scheduled to be finished by the end of April.
At the car park building roof-top the tennis court is complete. The car park building painting works are virtually complete as are the wire mesh and planter box façade installations together with irrigation systems. Security controls and access systems are now installed and being commissioned.
To see more construction update photos from Northpoint, click here or alternatively, follow Northpoint on Facebook.

|